Expand

Question 131.01

Question: Can an issuer assign proved undeveloped reserves to horizontal locations offsetting the toe of an existing horizontal producing well if the location is moving in the direction of other successful, analogous producing horizontal wells?
Answer: Yes, if the technical evidence supports this assignment with reasonable certainty. [Oct. 26, 2009]

Question 131.02

Question: Does the standard, "reasonable certainty of economic producibility," in the definition of "undeveloped oil and gas reserves" mean that a registrant cannot assign probable or possible undeveloped reserves beyond areas containing proved undeveloped reserves?
Answer: No. Reliable technology can be used to establish (1) that probable reserves in undeveloped locations are as likely as not and (2) that possible reserves in undeveloped locations are possible but not likely. [Oct. 26, 2009]

Question 131.03

Question: In the definition of "undeveloped oil and gas reserves," what "specific circumstances" would justify a time period longer than five years to begin development of those reserves?
Answer: Although several types of projects — such as constructing offshore platforms and development in urban areas, remote locations or environmentally sensitive locations — by their nature customarily take a longer time to develop and therefore often do justify longer time periods, this determination must always take into consideration all of the facts and circumstances. No particular type of project per se justifies a longer time period, and any extension beyond five years should be the exception, and not the rule.
Factors that a company should consider in determining whether or not circumstances justify recognizing reserves even though development may extend past five years include, but are not limited to, the following:
  • The company's level of ongoing significant development activities in the area to be developed (for example, drilling only the minimum number of wells necessary to maintain the lease generally would not constitute significant development activities);
  • The company's historical record at completing development of comparable long-term projects;
  • The amount of time in which the company has maintained the leases, or booked the reserves, without significant development activities;
  • The extent to which the company has followed a previously adopted development plan (for example, if a company has changed its development plan several times without taking significant steps to implement any of those plans, recognizing proved undeveloped reserves typically would not be appropriate); and
  • The extent to which delays in development are caused by external factors related to the physical operating environment (for example, restrictions on development on Federal lands, but not obtaining government permits), rather than by internal factors (for example, shifting resources to develop properties with higher priority). [Oct. 26, 2009]

Question 131.04

Question: The definition of "undeveloped oil and gas reserves" requires that the company have adopted a development plan with respect to the reserves. What constitutes adoption of a development plan?
Answer: The mere intent to develop, without more, does not constitute "adoption" of a development plan and therefore would not, in and of itself, justify recognition of reserves. Rather, adoption requires a final investment decision. [Oct. 26, 2009]

Question 131.05

Question: Would a company's decision to slowly develop a field in order to extend its economic life justify recognizing proved undeveloped reserves in the field beyond five years?
Answer: No. The company should not recognize undeveloped areas as proved undeveloped reserves if it does not anticipate initiating development in those areas within five years. [Oct. 26, 2009]

Question 131.06

Question: Rule 4-10(a)(31)(ii) states that "[u]ndrilled locations can be classified as having undeveloped reserves only if a development plan has been adopted indicating that they are scheduled to be drilled within five years…." (emphasis added). In comparison, the Petroleum Reserves Management System of the Society of Petroleum Engineers and World Petroleum Council states that "[a] reasonable time frame for the initiation of development depends on the specific circumstances …" (emphasis added). Is there a difference between the terms "scheduled to be drilled" and "initiation of development"?
Answer: No. [Oct. 26, 2009]
Expand Expand
Resize
Tools
Rcl

Welcome to Viewpoint, the new platform that replaces Inform. Once you have viewed this piece of content, to ensure you can access the content most relevant to you, please confirm your territory.

signin option menu option suggested option contentmouse option displaycontent option contentpage option relatedlink option prevandafter option trending option searchicon option search option feedback option end slide